Overview
-
Announcement Date: August 20, 2025
-
Total Ridership: 10 million (achieved on August 19)
-
Opening Date: August 26, 2023
-
Time to Milestone: 725 days since opening (six months earlier than expected)
Current Ridership
-
Weekdays: Approximately 18,000–20,000 passengers per day
-
Weekends/Holidays: Around 10,000 passengers per day
Opened Section
-
From JR Utsunomiya Station East Exit to Haga–Takanezawa Industrial Park
-
Length: Approximately 14.6 km
Pre-opening Forecast
-
Weekdays: About 16,000 passengers
-
Weekends/Holidays: About 5,600 passengers
-
Expected to stabilize within three years
Challenges & Future Measures
-
Ridership has consistently exceeded projections, leading to congestion during weekday morning commuting hours
-
Additional services under consideration